Wind loads and ballast for field scaffolding/temporary shoring are established using which set?
Choices
- (A) ACI-318
- (B) ASCE-7/IBC/owner rules + bracing, tie-backs, ballast, inspection per engineer
- (C) Engineer hunch
- (D) Color
Correct answer: (B)
ASCE-7/IBC/owner rules + bracing, tie-backs, ballast, inspection per engineer
Explanation
Temporary works per ASCE/SEI 37, OSHA, local codes.