When mill certificates arrive for rebar heats from an unfamiliar furnace track, how should traceability QA begin before cages are fabricated?

Choices

  • (A) Warehouse by coil weight tally only
  • (B) Cross-verify heat-mill chemistry reports and quarantine heats pending engineer release
  • (C) Borrow bars from neighbouring sites without QA
  • (D) Sample bends per crew folklore without QA plan

Correct answer: (B)

Cross-verify heat-mill chemistry reports and quarantine heats pending engineer release

Explanation

Heat quarantine avoids mixed chemistry in cages.