On a cold shift nearing minimum fresh concrete temperature, which field control best supports compliance before rejecting a pour?

Choices

  • (A) Add hot water at the truck without engineering notice
  • (B) Heat materials or use approved admixtures and log arrival/pour temps per the method statement
  • (C) Pour fast then leave elements uninsulated
  • (D) Skip temperature checks after the truck arrives

Correct answer: (B)

Heat materials or use approved admixtures and log arrival/pour temps per the method statement

Explanation

Temperature logs prove protective measures were active.