On a cold shift nearing minimum fresh concrete temperature, which field control best supports compliance before rejecting a pour?
Choices
- (A) Add hot water at the truck without engineering notice
- (B) Heat materials or use approved admixtures and log arrival/pour temps per the method statement
- (C) Pour fast then leave elements uninsulated
- (D) Skip temperature checks after the truck arrives
Correct answer: (B)
Heat materials or use approved admixtures and log arrival/pour temps per the method statement
Explanation
Temperature logs prove protective measures were active.