← Back to question bank

Before stripping props under important beams, what document should normally justify the timing under professional site control?

Choices

  • (A) Superintendent portrait ID
  • (B) Early-age strength backing (cylinder/cpm method) aligned to ITP or engineer release criteria
  • (C) Guess curing age from memory
  • (D) Verbal handshake with crews only

Correct answer: (B)

Early-age strength backing (cylinder/cpm method) aligned to ITP or engineer release criteria

Explanation

Strength evidence gates premature stripping risk.

Back to question bank →

Question 141 of 176