What is the primary jobsite purpose of scheduling strength cylinders with a major structural pour?
Choices
- (A) Decorate laboratory shelves
- (B) Provide cured specimens proving required strength ahead of stripping or successive loading
- (C) Replace field inspection entirely
- (D) Delay schedule without rationale
Correct answer: (B)
Provide cured specimens proving required strength ahead of stripping or successive loading
Explanation
Stripping and early loading hinge on cylinder breaks.