What is the primary jobsite purpose of scheduling strength cylinders with a major structural pour?

Choices

  • (A) Decorate laboratory shelves
  • (B) Provide cured specimens proving required strength ahead of stripping or successive loading
  • (C) Replace field inspection entirely
  • (D) Delay schedule without rationale

Correct answer: (B)

Provide cured specimens proving required strength ahead of stripping or successive loading

Explanation

Stripping and early loading hinge on cylinder breaks.