Field wants larger-diameter bars for the same count—what must precede the pour?

Choices

  • (A) Rely on vendor opinion only
  • (B) Secure engineer-approved substitution verifying strength, lap lengths, congestion, and fixing loads
  • (C) Change bars on site without paperwork
  • (D) Update weight summaries only

Correct answer: (B)

Secure engineer-approved substitution verifying strength, lap lengths, congestion, and fixing loads

Explanation

Larger bars can violate lap and spacing limits.