An electrical sleeve conflicts with bottom mat bars in a slab—what is best before the pour?

Choices

  • (A) Clip bars without telling anyone
  • (B) Hold placement and issue an RFI to reroute sleeve or re-detail steel with design approval
  • (C) Float the sleeve above the mat unsecured
  • (D) Pour then chip out later

Correct answer: (B)

Hold placement and issue an RFI to reroute sleeve or re-detail steel with design approval

Explanation

Cover and spacing need engineered fixes not field cuts.