Post-occupancy training, M&V, and formal O&M handover in LEED/ASHRAE-style programs mainly preserve (conceptual) what, versus first-year peak performance+design intent?

Choices

  • (A) Rebound to minimum code only, with no re-commissioning
  • (B) Controls+Cx outcomes, FM discipline, spares+interval+metering+OPEX budget+re-commissioning cycles
  • (C) Blower door as OR isolation
  • (D) Zero NPSH for all pumps

Correct answer: (B)

Controls+Cx outcomes, FM discipline, spares+interval+metering+OPEX budget+re-commissioning cycles

Explanation

M&V+O&M+FM+re-Cx+OPEX—persist savings and intent.