When contract documents “adopt” ASHRAE, IPC, NFPA, and EN references alongside local and owner standards, the defensible first step to resolve a conflict (conceptual) is:
Choices
- (A) Always pick the least stringent rule
- (B) Ignore the stamped/registered design basis+contract
- (C) Identify the governing code/law+AHJ+adopted edition+contract+stamped basis+write RFI/exception+PE seal
- (D) Delete MERV+OA+in all+...
Correct answer: (C)
Identify the governing code/law+AHJ+adopted edition+contract+stamped basis+write RFI/exception+PE seal
Explanation
Hierarchy+law+AHJ+stamped+contract+exceptions+document+PE+owner+AHJ+path.