If the engineer finds cubes cast at a pour were not in proper order, the correct follow-up, per the key, is which?

Choices

  • (A) Re-cast identical cubes the next day
  • (B) Rebound test only
  • (C) Assume ready-mix cert
  • (D) Verify with the batch plant and/or use cores

Correct answer: (D)

Verify with the batch plant and/or use cores

Explanation

Key: verify with plant / use core as appropriate.