If the engineer finds cubes cast at a pour were not in proper order, the correct follow-up, per the key, is which?
Choices
- (A) Re-cast identical cubes the next day
- (B) Rebound test only
- (C) Assume ready-mix cert
- (D) Verify with the batch plant and/or use cores
Correct answer: (D)
Verify with the batch plant and/or use cores
Explanation
Key: verify with plant / use core as appropriate.