Before casting a steel column base plate with a defined anchor-bolt pattern, what is the best practice to hold bolt positions until concrete sets?

Choices

  • (A) One-time eyeball layout without a template
  • (B) Use a fixed template or shop jig matching the pattern, check dimensions/angles, and lock against movement during pour
  • (C) Pour first and drill bolts later as needed
  • (D) Heat-adjust bolt locations during the pour without engineer approval

Correct answer: (B)

Use a fixed template or shop jig matching the pattern, check dimensions/angles, and lock against movement during pour

Explanation

Templates prevent pattern drift that breaks steel-to-base fit-up.