When early partial reshoring or prop removal is requested for a slab, what evidence best supports a controlled field release?

Choices

  • (A) Calendar age alone without tests
  • (B) Cylinder or approved strength evidence compared to engineer thresholds for the planned early load
  • (C) Verbal OK from a trade without numbers
  • (D) Strip props at shift end to accelerate work

Correct answer: (B)

Cylinder or approved strength evidence compared to engineer thresholds for the planned early load

Explanation

Early loads must meet documented strength limits, not guesswork.