Surface honeycomb appears on a column after early stripping—what should the contractor do first?

Choices

  • (A) Prime and paint décor finishes immediately
  • (B) Notify engineer, document depth, chip unsound concrete per approved repair plan if issued
  • (C) Pack voids with off-the-shelf cement without briefing
  • (D) Defer for weather to cure itself

Correct answer: (B)

Notify engineer, document depth, chip unsound concrete per approved repair plan if issued

Explanation

Engineering direction sets repair depths and bonded materials.