Why do some programmes keep reshores under lower slabs after upper forms are stripped?
Choices
- (A) For decorative sightlines beneath decks
- (B) Construction stacking and curing loads still pass through supporting slabs until the full frame matures
- (C) Concrete never transfers shear between floors
- (D) Upper shoring alone solves all tributaries blindly
Correct answer: (B)
Construction stacking and curing loads still pass through supporting slabs until the full frame matures
Explanation
Load paths follow pour sequence not a single stripping gate.